DAVENPORT, Iowa — Lanes on Brady Street will be closed as workers repair the sanitary sewer system.
The work will start on Monday, May 16, 2016 and will close the roadway’s two right (or eastern) lanes between Kirkwood Boulevard and 12th Street.
The entire project will be done along Brady Street in eight stages:
Stage 1: Kirkwood Blvd. to 12th St. – east two lanes – May 16 – June 6
Stage 2: Kirkwood Blvd. to 12th St. – west two lanes – June 6 – June 21
Stage 3: High St. to Kirkwood Blvd. – east two lanes – June 21 – July 2
Stage 4: High St. to Kirkwood Blvd. – west two lanes – July 2 – July 22
Stage 5: 12th St. to 6th St. – east two lanes – August 1 – August 18
Stage 6: 12th St. to 6th St. – west two lanes – August 18 – August 29
Stage 7: 6th St. to River Dr. – west two lanes – August 29 – October 3
Stage 8: 6th St. to River Dr. – east two lanes – October 3 – October 21
The City of Davenport said that dates could shift as the work progresses.